Fire breaks out at notorious construction site

Fire breaks out at notorious construction siteA fire broke out in Hanoi, on Saturday morning, at the accident-prone construction site of Vietnam’s tallest building.

The fire started at around 10:20 a.m. on the first floor of the 70-story Keangnam tower in Tu Liem District. 

City firefighters extinguished the flames just a few minutes later.

Choi Jae Ok, Keangnam's Administrative Officer, said that the building is still under construction and doesn't yet have a fire alarm system.

Some construction workers told Thanh Nien they did not know how to use the fire extinguishers available at the site.

The authorities are investigating the fire and assessing the damage.

South Korea’s Keangnam Enterprises Ltd. began work on the project in 2007.

When completed, the building will become Vietnam’s tallest skycraper, surpassing the current title-holder 68-story Bitexco Financial Tower in Ho Chi Minh City.

Despite its impressive height, the Keangnam project has become notorious for its poor safety record. 

In March, Hanoi authorities launched an investigation into the construction site following the death of six workers – two in February and four in July 2009.

In March, a fire broke out on the 25th floor of the project.

Last month, a piece of debris fell from the site severely injuring a woman who was passing below.

Related Articles

Fire breaks out at notorious construction site

Fire breaks out at notorious construction siteA fire broke out in Hanoi, on Saturday morning, at the accident-prone construction site of Vietnam’s tallest building.

The fire started at around 10:20 a.m. on the first floor of the 70-story Keangnam tower in Tu Liem District. 

City firefighters extinguished the flames just a few minutes later.

Choi Jae Ok, Keangnam's Administrative Officer, said that the building is still under construction and doesn't yet have a fire alarm system.

Some construction workers told Thanh Nien they did not know how to use the fire extinguishers available at the site.

The authorities are investigating the fire and assessing the damage.

South Korea’s Keangnam Enterprises Ltd. began work on the project in 2007.

When completed, the building will become Vietnam’s tallest skycraper, surpassing the current title-holder 68-story Bitexco Financial Tower in Ho Chi Minh City.

Despite its impressive height, the Keangnam project has become notorious for its poor safety record. 

In March, Hanoi authorities launched an investigation into the construction site following the death of six workers – two in February and four in July 2009.

In March, a fire broke out on the 25th floor of the project.

Last month, a piece of debris fell from the site severely injuring a woman who was passing below.

Related Articles

Tuesday, October 19, 2010

Central firm guilty of dangerous work

HA NOI — The Tin Nghia Trade and Construction Co Ltd was named and shamed after extremely poor quality work on the Dieu Ga Reservoir was discovered in Binh Thanh Dong Commune, in the central province of Quang Ngai, earlier in the week.

Nguyen Thuy, chairman of the commune's People's Council, said that leaders of the commune uncovered the shoddy work when examining the construction site on Monday.

He said that workers at the construction site of the dam had cut corners and used red soil and clay mixed with cement for the work, which was 90 per cent finished.

"No one mixes cement with this kind of soil to concrete a dam. They have to mix cement with gravel and sand, to ensure the quality of the work," Thuy said.

After taking the sample of the mixture for testing, it was found the mixture contained only 30 per cent of cement with the rest comprised of red soil, clay and waste sand, he said.

Initial investigations revealed that more than 40 metres of the breakwater had been built using the substandard mixture.

"It was total violation of construction quality controls," said Le Van Lac, a staff member at the provincial Irrigation Work Unit and Flood Prevention and Control unit.

Le The Thanh, deputy director of the Management Board of Investment Projects under the provincial Department of Agriculture and Rural Development, said the Tin Nghia Trade and Construction Co Ltd would have to remove the 40 metre-section of the dam and rebuild it.

However, Thuy said leaders and residents of the commune were also worried about the completed part of the dam.

"How are we to know if the construction was good enough or not? When the flood season comes, a badly constructed dam could break and leave us exposed to extreme risk," he said.

He said the commune authority had sent a document to Binh Son District's People's Committee to propose further investigation of the quality of the dam's construction. — VNS