Thursday, November 18, 2010

Vinacomin to review red mud disposal system: official

The state-owned Vietnam National Coal Mineral Industries Group (Vinacomin) will check the design of red-mud disposal lakes in the Tan Rai alumina plant following the recent red mud spill in Hungary, Vinacomin deputy director Duong Van Hoa told Tien Phong newspaper.
In an interview with Tien Phong on Wednesday, Duong Van Hoa said the red mud incident in Hungary has attracted the attention of the Party and State leaders as well as relevant ministries and agencies, and Vinacomin also watched closely the red mud spill of the world's first aluminum production industry in the last 100 years.
How is the Tan Rai project progressing?
Work on the Tan Rai alumina plant is entering its final stage. It is expected that the project will finish later this year, and the first product will come out early next year.
The project is about three months behind schedule due to the rainy season and several problems when importing equipment. However, the delay is not too serious for such a VND12 trillion (US$615 million) project.
What are the warnings that the Hungarian red mud spill can give the Tan Rai project?
I think it gives a very serious warning that makes us reconsider the design of the red mud disposal lakes in the Tan Rai alumina plant.
The plant is using Bayer technology. The equipment is not totally made in China but also in the EU, Japan and some in Vietnam. The main contractor is China’s Chalieco.
The disposal lake is designed by Samy Consulting Institute in Shenyang, one of the leading design institutes in China's aluminum industry.
The construction of the red mud disposal lake in Tan Rai is completely different from the one in Hungary. The one in Hungary is built on the lowlands while the Tan Rai disposal lake is located below the valley, protected by surrounding hills.
But the area has been hit by flash floods?
To prevent flooding in case of heavy rains or flash floods, we have designed the drainage system around the disposal lake to ensure water does not spill over the lake. When flash floods occur, water can not overflow the lake as the amount of red mud is not higher than surrounding hills.
We also studied the plan for earthquake resistance. We will review all the deigns of the red mud disposal system.
Some have raised concerns over the quality of works overseen by Chinese contractors. What do you think?
I have not seen any problems in the building of this plant by far. I was questioned a lot about why did not import equipment from the EU, the US or Australia.
If anyone thinks that we imported Chinese equipment because they are cheap, it is just one reason. There is another reason, that is the regulations. When the project is out there for bidding, there are very clear criteria. If their equipment are cheap but still meet world standard, they will win the contract.
What about the project’s economic effectiveness?
Regarding to economic effectiveness, we have calculated full costs and market conditions of the project.
This project can give a boost to economic development in the Central Highlands. It provides jobs to 2,000 local workers, and will require more services such as transport, and repairing services.
What about the profit?
It is calculated that the project will gain the profit of 11 percent. It is not high, but we must pursuit economic and social targets of the government.

Related Articles

Friday, October 1, 2010

Water shortage may delay first run of largest power plant

Water shortage may delay first run of largest power plantInsufficient water may make it impossible for the nation's largest hydropower project in Son La to start running at the end of this year as planned, a local weather expert said.

The Son La power plant began to receive water in mid May, but its water level was just 160 meters, below the "dead point" of 170 meters.

Nguyen Lan Chau of the Central Hydrometeorology Center said water levels have been low this year and will not improve soon due to the lack of rain. She said she was worried that Son La will not have enough water by the end of the year.

Chau also said two of the three largest hydropower reservoirs in the northern region, Hoa Binh and Tuyen Quang, have also seen water levels fall this year.

Construction of the 2,400-megawatt Son La power plant is scheduled to be completed in 2012 but its first unit is to be put on line in December.

The government in April had already forecast that lack of water in reservoirs could translate into a loss of nearly 1 billion kilowatt-hours of electricity at hydropower plants this year.

Nguyen Hong Ha, head of the Son La project, said water shortage was the “biggest difficulty” for the power plant now. However, he said he still believed that the plan to start running the plant on December 25 was viable.

The problem is that, by storing water, Son La could affect the operation of Hoa Binh power plant, which is located downstream the same river.

Hoa Binh is expected to generate 8.5 billion kilowatt-hours this year but the plant’s general director, Nguyen Van Thanh, said it may have to cut the target to 7.5 billion.

Related Articles

Water shortage may delay first run of largest power plant

Water shortage may delay first run of largest power plantInsufficient water may make it impossible for the nation's largest hydropower project in Son La to start running at the end of this year as planned, a local weather expert said.

The Son La power plant began to receive water in mid May, but its water level was just 160 meters, below the "dead point" of 170 meters.

Nguyen Lan Chau of the Central Hydrometeorology Center said water levels have been low this year and will not improve soon due to the lack of rain. She said she was worried that Son La will not have enough water by the end of the year.

Chau also said two of the three largest hydropower reservoirs in the northern region, Hoa Binh and Tuyen Quang, have also seen water levels fall this year.

Construction of the 2,400-megawatt Son La power plant is scheduled to be completed in 2012 but its first unit is to be put on line in December.

The government in April had already forecast that lack of water in reservoirs could translate into a loss of nearly 1 billion kilowatt-hours of electricity at hydropower plants this year.

Nguyen Hong Ha, head of the Son La project, said water shortage was the “biggest difficulty” for the power plant now. However, he said he still believed that the plan to start running the plant on December 25 was viable.

The problem is that, by storing water, Son La could affect the operation of Hoa Binh power plant, which is located downstream the same river.

Hoa Binh is expected to generate 8.5 billion kilowatt-hours this year but the plant’s general director, Nguyen Van Thanh, said it may have to cut the target to 7.5 billion.